15 – Nipple Up BOP

26 November 2008

Alert 08 – 39 Dropped Object: Thermal Tree Cap (TEA Cosy) Falls Resulting in Fatality

Alert 08 – 39 Dropped Object: Thermal Tree Cap (TEA Cosy) Falls Resulting in Fatality WHAT HAPPENED: The operation was utilizing a rig crane to move a subsea
26 August 2008

Alert 08 – 26 Fall from Height Results in Double MTO

Alert 08 – 26 Fall from Height Results in Double MTO WHAT HAPPENED: Two Floormen were working in the substructure approximately 4 metres (13.4 feet) above the
26 June 2008

Alert 08 – 21 Installing Annular BOP Results in RWC

Alert 08 – 21 Installing Annular BOP Results in RWC WHAT HAPPENED: The injured party (IP) was assisting in the installation of the annular preventer to the
26 March 2008

Alert 08 – 12 Fall From Height Results in LTI

Alert 08 – 12 Fall From Height Results in LTI WHAT HAPPENED: Two roughnecks were working in BOP area to reposition the telescopic bell nipple. After working
26 February 2008

Alert 08 – 08 LTI – Struck by Flowline and Fall in Substructure

Alert 08 – 08 LTI – Struck by Flowline and Fall in Substructure WHAT HAPPENED: A crew was rigging down the flow-line that extended from the bell
26 January 2008

Alert 08 – 01 Working with Rotating Control Devices

Alert 08 – 01 Working with Rotating Control Devices WHAT HAPPENED: Incident #1 – The rotating control device (RCD) was leaking so the driller sent an employee
1 October 2006

Alert 06 – 35 Release of Pressure Results in Laceration and Sutures

Alert 06 – 35 Release of Pressure Results in Laceration and Sutures WHAT HAPPENED: While pressure testing the Choke Manifold up to 15,000psi the Assistant Driller noticed
1 September 2006

Alert 06 – 32 Residual Pressure in BOP Results in Finger Being Trapped

Alert 06 – 32 Residual Pressure in BOP Results in Finger Being Trapped WHAT HAPPENED: The IP was assisting in the operation to close the BOP doors.
1 March 2006

Alert 06 – 11 Near Miss – Equipment Failure at 14,000 PSI

Alert 06 – 11 Near Miss – Equipment Failure at 14,000 PSI WHAT HAPPENED: During a pressure test on the choke and kill line of a subsea